TECHNICAL SPECIFICATIONS CONCERNING MATERIAL
INSPECTION AND THE CONSTRUCTION OF
CONTENTS
2.2 CONSTRUCTOR’S DUTIES AND LIABILITIES.
2.3 QUALITY AND CHARACTERISTICS OF
THE MATERIALS TO BE EMPLOYED.
2.3.1.1 Materials subject
to protective surface treatment.
2.3.1.2 Self-protecting materials
3.4.1 RULES AND
INSTRUCTIONS CONCERNING STRUCTURAL DETAILS AND WELDED JOINTS.
3.4.1.1 General indications
: aspects of project design.
3.4.1.2 General indications: construction aspects.
3.4.1.3 Advice concerning welded joint details :–
edges
3.4.2.2 Welding methods specifications
3.4.2.3 Applicable welding
methods.
3.4.3 WELDING PROCEDURE SPECIFICATION QUALIFICATION
3.4.4 QUALIFICATION OF PERSONNEL
EMPLOYED IN WELDING ACTIVITIES.
3.4.4.1 Welders and welding
operators.
3.4.5 WELDING EXECUTION
METHODS
3.4.5.2 Pre-heating and
interpass temperatures.
3.4.5.3 Special
prescriptions.
3.4.6 WELDING DURING THE
ASSEMBLY STAGE ON SITE.
3.4.7 NON-DESTRUCTIVE
CONTROL CHECK METHODS
3.4.8 INSTRUMENTAL
CONTROL CHECK RANGE
3.4.8.2 Instrumental control checks.
3.4.8.3 Intensification of controlcheck after negativ results
3.4.10.1 Repairs without new
welding operations.
3.4.10.3 Hollow repair execution
3.4.11 CONTROL CHECKS ON PRODUCTION TEST PLATES
3.4.12 WELDING ACTIVITY
REPORT.
4 SECTION 4:
NON-WELDED JOINTS
4.2.3 JOINTS WITH
FRICTION BOLTS.
4.2.7 DIMENSIONING TESTS
ON SINGLE PIECES.
4.2.8 TOLERANCE LEVELS FOR WELDED BEAMS AND ASSEMBLED
ELEMENTS.
4.2.9 PAINTING AND
PROTECTIVE COATINGS.
The
present specifications define the criteria to be adopted for procurement
testing and controls on workshop production of materials for metal girding, as
well as all control checks to be performed during provisional acceptance and
construction assembly and installation.
The
present specifications are applicable to all metal structures and mixed steel
and concrete structures for the construction of railway bridges.
The
present specifications are correlated with European standards currently in
force, and in particular the standards listed below:
For all metal
structure construction the Railways must employ a suitable Construction company
specialized on «Construction, assembly and installation of metal structural
work» with an internal organisation capable of managing all construction and
welding activities in the workshop and/or on site realisation of the contract
work.
The
constructor must demonstrate a quality system according to EN 729-2-3 and
EN ISO 9001:2000 standards certified by an accredited EWF and SINCERT
organisation.
The
following requirements are necessary in particular:
·
Welders certified by an
accredited SINCERT organisation
according to EN 287 standards;
·
Welding procedure certified
according to EN 288-3 standards;
·
The constructor must have
performed a railways steel bridge for one of Railways Company of one European
Union Countries, in the same fields as those included in these specifications,
in the last two years ( to be demonstrated with an appropriate declaration
signed by the competent organisation)
·
The constructor must possess his
own accredited workshop according to EN
CEI 45001 standards.;
·
The constructor must possess
an NDC sector (non-destructive control )
according to EN ISO 9001.2000 standards
certified by an accredited SINCERT and EWF organisation and employ certificated
level 2 personnel according to EN 473
standards;
The application of the present Technical
specifications does not relieve the constructor of the drawing up of the Quality
Plan and the Quality Control Plan, which are obligatory.
The
aforesaid document must be presented to the Railways who reserve the right to
make any necessary modifications. It remains understood that said document must
be approved by the Project design engineer and the WS.
The constructor must present the Railways and Work Supervisor
(WS) with two copies of the workshop plans as well as the lists of all
materials necessary for girder construction.
Any eventual replacements or changes in either profiles or structures
that the Constructor may decide to make compared to the indications included in
the approved plans, must be requested prior to modification, explaining the
reasons for any changes, and the WS will have the sole and unquestionable right
to authorise said changes or not.
In cases where
the Constructor is not able to procure rolling plates, these may be obtained
from sheet metal cut with oxyacetylene flame, plasma, laser or by mechanical
means, but in this case the various pieces must be cut so that the rolling
direction of the plates coincides with the predominant stress direction of the
plates.
The steel used for all main
structures such as load bearing beams,
“I” beams, cross beams, bracing, joint covering, plates and node point
squares plats, must comply with the following quality
standards:
|
S275
C/D1 EN 10025/90 (now S275 JO /J2G3) S355
C/D1/DD1/DD2 EN 10025/90 (now S355JO /
S355J2G3 / S355K2G3 / S355K2G4) |
Where more precise information is not available, the
quality grade choice will be made according to the following table:
|
Temperature for performing Charpy V resilience tests (Minimum
required value on an average of three standard tests: 27 J) |
||
|
Steel thickness (mm) |
Important
elements subject mainly to traction or fatigue (even if
compressed) |
Important elements subject to static
compression or secondary elements |
|
s ≤ 25 |
T
= Tm |
T
= Tm + 20 |
|
25
< s ≤ 40 |
T = Tm - 10 |
T =
Tm + 10 |
|
40
> s ≤ 50 |
T =
Tm -
20 |
T =
Tm |
|
s > 50 |
T =
Tm -
20 T = Tm |
T = Tm |
T = Temperature for
performing Charpy V tests (°C)
Tm= Minimum working
temperature (°C) to be established in agreement with the WS.
All
mechanical and chemical characteristics must comply with EN 10025 standards
For steel plate destined
for composite profile construction with partial and complete penetration
welding (except for composite profiles with butt welding), or in any case even
with fillet welding, where the plate is subject to stress in the direction
transversal to the rolling direction ( e.g. cross joint) ductility levels must
be controlled through transversal traction tests according to EU 10164 standards with class 3 average
pinching with Z35 rupture point for S275 (ex Fe 430) plates and Z25 rupture point for S355 (ex Fe 510)
plates.
For structural
elements not destined for welding, the instructions according to EN 10025standards for S275 C and S355 C steel apply.
In this case silicon killing is permitted.
The use of materials that are
self-protective against environmental corrosion is permitted: S355 C2KI now
S355JOW, S355J2G1W, S355K2G1W, S355K2G2W.
The mechanical and chemical characteristics must comply with EN 10155 standards.
S235JR EN 10025 may be used for secondary
structures such as guard railings, plank support bars, foot-guards and any
elements that are not part of the main structure .
S235JR EN 10025 is to be
employed for striated or meshed plate for planking or foot-guards. This plate will have
a thickness of 5 mm + 2mm striating.
Grate planking
must be made from cell-structured hot galvanised grating with 30 x 30 mm mesh,
bearing plate 30 x 3 mm, and secondary rod 20 x 3 mm, or some other type with
equivalent characteristics in weight and capacity. The steel material used is
show on EN 10025.
All
materials employed must be ordered with tests to be performed according to EN 10204 standards, item 3.2 of prospectus I
and supplied so that they result unquestionably as qualified products. The
supplier and/or foundry must identify all pieces with a nucleated punch showing
the casting and plaque number. The
certificate of origin issued by the manufacturer according to EN 10204 standards, must contain the chemical
composition of the casting analysis
prescribed in prospectus II of EN 10025 standards.
The
following tests must be performed in relation to the aspects described above:
All
profiles, plates, large sized plates and sheets must be subjected to mechanical
and chemical tests on three samples taken from each 400 KN, or fraction
thereof, of materials obtained from the same casting and with thicknesses that
do not differ more than 4 mm ( for C, T and double-T shaped bars, reference
will be made to the wing thickness);
Specimens will be taken from each sample for the
following tests:
1 traction test
3
resilience tests
1
bending test (where specified)
1
chemical analysis (for each casting)
1
pinching test (where specified)
It must be remembered that in order to belong to the same 40t test unit,
the plates must have been subject to the same processing cycle and heat
treatment.
For plates, large-sized plates and sheets destined for
welded profile construction, as well as the tests relative to mechanical
characteristic control checks according to
EN 10025 standards, other tests must be performed according to
agreements established with the supplier on
material order by the Constructor, relative to the additional limits
described in the paragraph «Materials
Subject to Protective Surface Treatment»;
Surface condition and dimensional characteristic tests
must also be performed on all materials.
The aforesaid tests must be performed in foundries and
the results of all tests must be included in the product quality certificates
issued by the foundry in question.
Bolts will be exclusively «high resistance type».
Bolt types will be selected according to the type of joint necessary,
and in particular:
for joints with slot bolts: EN 20898 1st part : class 8 nuts
For friction joints: class 10.9 screws EN 20898 1st part: class
10 nuts
In both types
of connection the washers and plaques will be in C50 EN 10083, tempered
drawn steel with hardness : HRC 32 ¸ 40.
Refer to prospectus II and III EN 20898 for mechanical and chemical
characteristics.
All nuts, bolts, screws etc must be
certified according to EN 20898
standards by the manufacturer.
All materials must comply with the
following prescriptions:
Stake connectors
Steel
suitable for stake connector manufacturing and compatible for welding with the
material of the structural element in relation to the stakes; the product
should be marked with the following mechanical characteristics and be included
in the product certificates:
-
fy ≥ 350 N/mm2
- fu ≥
450 N/mm2
- Elongation: ≥ 15% - - -- Pinching:
≥ 50%
All welded stakes will be
subjected to visual control checks to ensure that no discontinuity exists in
the metal collar after welding.
No cracks are permitted in
stake welding.
Bending tests
will be performed on 5% of the
stakes.
Connectors
produced from profiles, plates etc.
A steel equivalent to that used for the structural
element to which the connectors are welded.
For
instructions concerning support equipment, refer to the project drawings that
must contain all fundamental equipment characteristics .
This chapter refers to the welded joints on
metal railways bridges using arc welding methods. The instructions include the
prescriptions for welding procedure, the personnel employed for welding
operations, and joint control checks, and the relative control certification,
and provides all prescriptions concerning structural details and welded joint
details, as well as all relative operating and control methods.
The instructions included in current ENV 1993/1
standards can be applied to all welding calculation methods.
Welding : connection
of two solid parts that form the continuity of the material between the united
parts.
Electric arc welding : Autogenous welding process through fusion where
the heat source is composed of a voltaic arc that flashes between two
electrodes.
S1 Thickness greater than joint
S2 Thickness
less than joint
L Welded
seam length
Gpp Caulk
depth
p Penetration depth
a=g Welding
seam groove height
Lp Welding
seam slanted side
z Welding
seam side
a gusset
slant angle
w Angle
between to elements to be joined
HI Specific
heat input
I Welding
current
V Welding
voltage
v Translation
speed from heat source
WPS Welding
procedure
Z Pinching
CEV Carbon equivalent
Tpr Preheating and interpass temperature
d Space clearance between adjacent surfaces
L1,L2 Length of adjoining reflectors
The admissible stress levels permitted for basic
materials and welding are those indicated in the Standards adopted for the
project.
1 During the
project design stage, priority must be given to easy assembly of the various
structural elements, to make accessibility convenient for the welder.
2 When uniting structural elements
through welding, the joint types must comply with the following:
· Full
penetration butt joint;
· Full
penetration T joint;
· Partial
penetration T joint (with a bevel of at least 1/3 of the minimum thickness used
and the seam side at the foot ³ ½ of the
same thickness);
· T joint
with corner seams;
·
Lap joint with corner seams.
Full or partial
penetration joints and the preparation of the edges that will be included in
the drawings or on the edge tables for revision where necessary, will be
defined by the Constructor after prior approval by the control organisation,
and will be approved by the Railways.
For butt welding of
two main elements of different thickness, the thicker element must be gradually tapered until it is equal to the
thickness of the thinner element.
For full penetration
T joints the welding must be gradually widened until the width is at least
equal to 1.3 times the thickness S1 (minimum employed thickness) of the plate
on which it will be attached (fig. 2.3) :
L ≥1.3 S1
To guarantee an adequate
joint between the core and the platband.
For
partial penetration T joints, where no particular instructions are specified
for edge preparation, assembly, and control of final measurement, the caulk opening angle must not be less than 45°
and the height of the resistant section will be assumed as being equal to the
depth of the caulk «gpp» (fig.2.5).
For joints with
corner seams, the height of the theoretical groove «g» is calculated starting
from the theoretical caulk vertex; in general the «g» grooves should be
appropriately sized and in any case no less than 4 mm, or half the thickness of
S1, if this is thicker than 8 mm.
In cases where
different project instructions exist, the height of the groove «g» will be the height of the resistant section to
be considered in calculations. (fig. 2.1).
The side of the
corner seams «z» (fig. 2.2) that unite the two plates with thicknesses S1 and
S2 (S1 < S2) must be sized adequately so that they satisfy the calculation
conditions, and normally, also the following limit:
S1/2 ≤ z
≤ S1
For thicknesses S2 >10 mm it is better to apply
the rule z ≥ z1,
on condition that it is not in conflict with the previous limit.
The z1 limits are shown in the
following prospectus:
|
S2(mm) |
10÷20 |
30 |
50 |
70 |
100 |
|
z1(mm) |
5 ÷ 6 |
8 |
11 |
13 |
14 |
The shape of the seam
or the first pass in multiple pass joints, must respect the following relation
indicated between the width (Lp) and the
depth (g + p):
0.5 Lp ≤ g+p ≤ 1.1 Lp
where p
= penetration depth;
Lp=
the slanted side of the welded seam.
The control check of the correct seam form will
be performed using production standards.
In the case of overlapping platbands (e.g.
beams with uniform resistance) in the area of the end section of the overlapped
platband, an adequate joint must be guaranteed between the double layer and the
platband, however, a closing corner seam must be added in any case, with a
groove height that is at least half the height of the thickness of the
platband, and united to the side seams.
3 It is possible for beam core transversal stiffeners
not to be welded to the stretched platbands; in this case they must be
positioned at a distance more than 25 mm, and no more than 5 times the core
thickness, from the platband level surface in order to permit the placing of
the seam around the end of the stiffener. (fig. 2.7).
When welding the core
stiffener to the platband, the foot of the seam must be smoothed using a
grinder to make any variations in shape gradual and to eliminate any possible
notching.
4 For the construction of elements composed of caissons, that are
internally inaccessible, according to the project design requirements and
compatible with the destination of the structural element, a ½ V must be
prepared (cut into the plate with the lesser thickness) with a support plate or
with corner seams as shown in figures 2.8a and b. Permanent metal supports are
forbidden for elements subject to fatigue.
5 Particular care must be taken in the construction of elements in which
the platbands meet at an angle that is fairly acute, such as those used to form
«gussets» (fig. 2.9 ). The platband of the gusset is welded to the platband of
the beam until the welding has penetrated the vertex deeply ,the opening of the
angle α will depend on the beveling of the angle ω formed by the two
elements to be united together; their relation will be that established by the
UNI 11001 table, as follows:
|
|
20° ≤ ω < 50° |
|
α = |
70° |
|
|
|
50° |
≤ ω
≤ 70° |
|
α = |
60° |
|
70° |
< ω <
90° |
|
α = 50° |
||
The space at the vertex of the joint will
be ≥ 3 mm.
6 The connecting joints between core and platband
on the main beams (bridle bars of the reticulated girders or
longitudinal girders for solid walls) will generally be executed with
appropriately sized corner seams.
In cases where the
rails are positioned near the core, the
core- upper platband joints on the girders must normally be full penetration type, unless otherwise
specified according to the instructions in item 5 section 3.4.1.2.
The core – upper platband joints of girders on mixed
structure scaffolding will be executed in the same manner. The node points of the lower bridle bars on reticulated girders, the
fixing gussets of the transversal beams or any other zones that are
particularly important will normally be executed with strong penetration
joints, except in the case of butt node points that require full penetration.
In any case, when the beam is executed with corner seams outside the node point
zone, the core edges must be changed gradually (from grooved edge to right
angled edge) for a length no less than 300 mm (transition zone).
In
the case of mixed structure bridges with ballast, for slab thickness generally
greater than or equal to 40 cm, partial penetration will be permitted for
welding between the core and the upper platband.
1
Particular care must be taken to avoid sharp angled cuts or openings. All
openings and cuts made using any method whatsoever must have well-rounded
corners; alternatively but only subject to prior authorisation by the State
Railways, these connections could be replaced by holes drilled at the vertex of
each angle.
2 The vertex on the
corner seams must be completely united.
3 When butt welding T or double T beam elements
together, the platband and core joints will normally lie on the same section.
In certain cases, the core and platband
joints can be staggered according to a Z formation, studied appropriately for
the purpose.
When butt-welding the
platbands an access opening must be arranged on the core to guarantee access to
the welded joint from all sides during execution and control.
A
normal semi-circular access opening with arc of a circle ends could be placed on the
core for this purpose. Wherever there is severe stress or fatigue or where
direct load is applied on the platband, an elongated grooved access
opening will be applied so that it can be
welded in closed position after the core and platband joints have been
completed and the relative non- destructive control checks have been performed.
( figures. 2.11 a, b ).
In any case, for all core
and/or platband butt welding , before beam composition, and after the
prescribed non-destructive control checks, the welding area on the platband or
the core in question must be smoothed before assembling the beam elements for
corner welding.
4 In the case of a
junction formed by three or more structural elements ( for example in a
composite beam cross welded between core, platband and stiffening ribs)
adequately sized access openings must be foreseen to permit correct joint
welding and control checks. (figures 2.7 - 2.12).
The access openings must be arc of circle, or
in any case in a conveniently shaped form . The welding seams that reach the
access opening edge must be welded around it.
5 Wherever there may be any danger of lamella
tearing, the constructive details must be designed so that they prevent or at
least minimize the retraction tension in unfavorable directions, that is , in
directions perpendicular to the rolled surface.
Several methods can be
used to avoid these situations such as :
·
plan
the assembly sequence with great care so that welding is performed with the
least restriction possible;
·
modify
the order of pass execution;
·
perform
buttering on any unfavorably orientated rolled surfaces;
·
perform
partial penetration seam welding with prepared edges .
In certain cases,
rolled materials can be used with reduced microinclusion
content or even forged elements instead of rolled materials.
With a view to
minimizing the danger of lamella tearing, for full penetration T joints, the
expression that provides the welding width at the foot ( L = 1.3 x S1 ) is considered valid for the values S1 ≤ 1/3 S2 (fig.
2.3).
Where these
conditions are not satisfied and the thickness S2 is more than 40 mm, the value
of L must be increased gradually until it reaches a value equal: L ≥ 2 x
S1.
Automatic heat cutting ( flame-cutting or
plasma) is recommended, or cutting using tool machines such as planes and
cutters that are essential for U and J beveling etc. manual or automatic
flame-cutting or other methods are
permitted where surfaces are finished later with precision grinding to remove
all traces of cutting grooves and other rough surfaces.
1 The welding methods taken into consideration
are the electric arc welding methods described in item 3.4.2.3.
2 All welding will be
performed using a specific heat input(HI), calculated according to the formula
:
HI = 0.06 x I x V / v (kJ/mm)
where : I = welding current
(A),
V = welding voltage (V),
v = translation speed from
heat source (mm/min),
that does not diverge from the measured value
by more than 20% during test trials for welding technique qualifications. Generally
the maximum heat input will be 2.8 kJ/mm
while the minimum should not result any lower than 0.8 kJ/mm.
3 All
equipment necessary for performing welding operations must be in perfect
working condition and their fundamental characteristics must be controllable by
the State Railways.
Welding method
specifications must be calculated for every joint to be performed in production
by the constructor company. Calculation methods for welding methods must comply
with the instructions provided in EN 288 standards, part I.
All
welding methods must result as qualified according to the instructions provided
in the following chapter.
The welding methods in
question in these technical specifications are as follows:
· Manual
shielded electrode welding;
· Automatic
submerged arc welding;
· Semiautomatic
and automatic continuous arc core
welding with gas protection
·
Manual,
semiautomatic or automatic welding for connectors;
• semiautomatic and
automatic full continuous arc welding for civil and industrial structure
welding; for bridges, this use is limited to secondary elements such as
handrails and planking elements.
When using continuous arc
methods, robot systems may be used . However, in general, automatic type
welding is preferable.
Other methods may be
authorised in special cases, after qualification tests, non destructive control
checks, and approval by the WS.
For this purpose, the
Contractor must present precise technical proposals concerning the
qualification and control methods for the particular case in question.
1 Comments
concerning weld material
The weld materials
employed must be able to guarantee deposit mechanical characteristics as
similar as possible to the basic materials. In particular, the difference
between the minimum values in the specification tables between the yield stress
of weld materials and those of the basic material must not exceed 100 N/mm2.
The tenacity of the
basic material and the weld material deposit must be calculated using the same
type of technological testing. The difference between the minimum values in the
specification tables between the tenacity of weld materials at an established
temperature must result as being at least equal to the basic material.
In general, the
chemical composition of the deposit should be substantially equivalent to that
of the basic material.
With steel possessing improved resistance to
atmospheric corrosion, weld materials for normal C/Mn steel can be used, except
for the last two finishing layers where, in any case, it is necessary to use weld materials with an
adequate percentage of Cu-Cr-Ni at least equal to 10% more than that of the
basic material, especially in the case of Ni, that must not result less than
1.5 %.
.2 Manual
method using shielded electrode welding;
For
S275 and S355 type steel, E44 and E52 series , quality class 4, basic
electrodes must be used.
These
electrodes must be marked with the symbols that provide a guaranteed Kv
resilience value at least to the minimum temperature of the basic material
tests (e.g. Kv 00 for JO type; Kv 20 for J2 type, etc.).
The
Constructor is bound to indicate the commercial brand of the electrodes he
intends using for welding operations.
The
use of non-homologated electrodes is permitted only after method qualification
tests as established in item 2 of 3.4.3.1.1.
3 Automatic
submerged arc welding method
Automatic submerged arc welding could
be used in the version with a single arc or twin arc welding head or with
several welding heads, in the single head version or opposite head version.
The
choice of the arc-flow combination must be made to guarantee that the deposit
mechanical and composition characteristics are the same as those of the basic
material.
As
well as all the other general characteristics necessary for other methods,
welding procedure for jointing using submerged arc welding must also include all aspects necessary for identifying the
welding installation, number and arc layout, as well as the location of the
welding heads compared to the joint.
4 Arc welding method with gas
protection
The
welding position must be indicated in the welding method specifications
relative to this procedure.
The protection gas must be a blend such as Ar-CO2, Ar-CO2-O2, Ar-O2 with a dew point
that must not be lower than -40°C. Pure CO2 can be used if recommended by the weld material manufacturer.
5 Connection
welding procedure.
Connectors for
adjacent slabs can be welded to the platband using semiautomatic core
continuous arc welding (NOT to be used for stake welding). Stakes must be
welded using shielded electrode or automatic methods.
For
this case, the only welding method permitted is the use of a de-oxidizing
capsule on the end of the stake and ceramic ferule.
The platband surface in
the connector welding zone must be cleaned in the same manner as any other
welding edge .
All welding procedure
specifications for structural construction must be qualified according to the
instructions in the items listed below and accepted by the Railways before
manufacturing start-up.
1 Welding procedure qualification
tests.
In general, except
for cases described in item 2 in 3.4.3.1.1, welding procedure specifications
must be qualified and certified according to
EN 288 part 3 standard requirements..
Welding procedure
certification must be issued by an Official Organisation.
2 Homologated
materials
Welding procedure
qualification tests do not need to be performed for manual welding with
shielded electrodes homologated on steel with resistance class up to 510 N/mm²
(S355).
Welders involved in
production for manual and semi-automatic welding application must be qualified
according to EN 287 Part 1 standards,
for all work positions and procedure in use. Welders who will be working in the
present contract context must pass a welding test including a T joint with
corner seam to be evaluated according to the standards described above.
Personnel working on
automatic and robot welding systems must possess EN 1418 certification.
Welder qualification must be
endorsed with the demonstration of the appropriate qualification certificate
issued by an accredited SINCERT and EWF organisation.
The Constructor’s
welding coordinator must keep records in a special register for this purpose,
of all qualified welders and operators, updating the records according to any
qualification variation (class extension, renewal) .This register must also
contain all periods of inactivity by all welders and/or operators in relation
to specific methods.
Both the register and the
qualification certificates must be available in the Constructor’s plant and
presented to WS personnel on request.
Furthermore, the WS has the
right to request new qualification testing whenever welding results show faults
or defects that can be attributed to insufficient professional capacity.
1 Before beginning any welding operations, the
edges of the parts to be united and the adjacent zones for a width of 100 mm
must be subject to visual and instrument control checks to ascertain the
absence of any cracks or flaking, and to ensure the correct preparation
conditions. No welding repairs are permitted on edges and the aforesaid
adjacent zones.
The main element edge
surfaces to be welded must be examined previously using a magnetoscope.
In the case of full
penetration cross joints specific ultrasound control checks (EU160 cl. B) must
be performed on the intermediate plate area to be jointed to guarantee the
absence of flaking or excessive segregation (at least 100 mm on each side of
the joint). This ultrasound control can be omitted for steel plate with
guaranteed striating in the direction of the thickness ( Z > 25% for
material S355, and Z > 35% for material S275, according to EN 10164).
2 Electrode
or arc switch-on must be performed on the appropriate auxiliary production test
plate placed or tack-welded at both ends, or in groove.
The use of end
production test plate is obligatory in any case, for all butt welding, for
automatic welding, and for all details where welding must be sealed afterwards,
as in arc stiffening on platbands.
3 The welders and the welding operators are
responsible for controlling the surface of each pass to ensure the elimination
of all scoria, profile defects and surface irregularity or roughness. If the
results are not satisfactory, the area must be subject to grinding before
performing the following pass.
4 On all butt and full penetration
corner seams, as a general rule the reverse side grooving should be performed
followed by a restart. Subordinately, a support plate or welding without
grooving can be performed by welders with special class qualifications.
5 For
automatic stake welding, each time a welding stage is begun on framework, each
welder must submit the first two welded stakes for control checking; if the
visual check is satisfactory, the stakes will be hammered to a 45° bend. After
bending, they will be straightened and must not show any signs of cracking or
lack of fusion.
If
this control check shows negative results, the Constructor is bound to
re-organise the welding technique on auxiliary plates and repeat the tests on
the first two welded stakes on the same framework, a second time.
All
stake welding in the workshop or on the work site must be performed exclusively
by personnel with specific experience. The personnel in question must
demonstrate their knowledge of machine setting parameters and welding
specifications by performing a practical test before the Railway
representatives or nominated control organisation.
6
Special care must be taken during piece assembly, providing for spot-welding to
safeguard pieces from wrenching from base materials or from welding
defects. In particular, wherever
possible, assembly U-bolts must be used ; the U-bolts must be removed by
grinding the relative welding seams.
Joints can be
assembled with welding points (spots) as a rule, no shorter than 50 mm in
length, removable during the execution
of the welded joint.
In butt joints that
are grooved back to front, spot welding is performed on the rewelding side.
Any points/spots to be
incorporated in the welded joint must be ground at the edges and examined
during welding operations; all cracked areas must be automatically eliminated.
In the case of
welding on ceramic plate, as a rule, groove spot welding is not required.
Pre-heating application on a
welded joint before welding execution, and maintaining the temperature during
welding are some of the factors that determine the welding heat cycle, together
with the thickness of all the structural elements that make up the welded joint
(combined thickness in fig. 6.1) and the specific heat input. In turn the heat
cycle produces different metallurgical structures in the molten area and in the
thermally altered area of a joint according to the chemical composition of the
base material and the weld material.
1 It is strictly forbidden to perform welding
using any method whatsoever when the environmental temperature is lower than
–5C.
2 The Constructor’s
workshop must be equipped with a depot for stocking welding material (electrodes,
arcs, flux, etc) that is perfectly closed and with a relative humidity level no
higher than 50%.
3 Once the original
packing of the fluxes and electrodes have been opened, they must be dried at a
temperature between 350° - 400° C for two hours and preserved in an oven at
150°C until the moment of use.
Non-melted flux can
be recovered and reused if mixed with new flux (mixture of 30% of previously
used flux with 70% of new flux). At the end of the work shift, any unused flux
must be removed from the machines and stocked in a special container. It can be
used again later after drying procedure as described above.
The efficiency of the
electrode and flux drying and preservation for submerged arc welding may be
controlled on Railway’s request, by checking the diffusible oxygen content
conducted on the deposit, using the testing methods described in AWS A4.3,
standards: mercury column technique
(required value < 5 ml/100g).
4 When performing T
joints or overlaid lap joints with corner seams, the surfaces that are in
contact with each other must adhere well. In these joints the maximum tolerance
distance is «d» (fig. 6.2), within the limits indicated below, and in any case
with adequate seam increase:
· In the
case of manual and semi-automatic welding: d = 1 mm for thicknesses less than
or equal to 10 mm; d = 2 mm where the minimum thickness of the joint is greater
than 10 mm;
· In the
case of automatic submerged arc welding : d = 1 mm.
5 For the terminal
section of the joint between the core and the platband on T beams and double T
beams, executed with inter-penetrating seals , as a rule, no welding should be
performed for a length of 150 mm before the execution of butt joints between
the beams.
To permit correct butt joints on profiles, in the case where the
core – platband joints result as complete, a section of about 150 mm of the
core-platband welding must be eliminated from each side of the joint (unseaming).
As
a rule with butt joint welding the operation sequence is as follows:
·
Preparation
of the edges to be welded and the elimination of the core ends;
·
Assembly and spot welding of the structural elements
(core joint space is larger than the platband space);
·
Platband welding preferably at
the same time, or through partial alternating filling on both platbands;
·
Core welding;
·
Core
to platband welding in the unseamed areas..
On
the other hand, in the case of beams welded with corner seams, a transition
area of about 200 mm must be foreseen (figure 2.11).
6 As a rule, all elements
united incorrectly must be cut and re-welded.
7 Any structures deformed
as a result of welding must be straightened by localised heat application or
heat straightening using mechanical means.
The welded joints of
elements subjected to straightening must be examined using adequate
non-destructive control methods after straightening according to the extension
and the type of joint.
The temperature of
the heated area (generally about 600°C) will be defined according to the base
material supply status.
The parts heated during
straightening must be substantially free of all stress and external force,
except for those resulting from the mechanical means used during heat
application.
1 Welding during assembly stages on the work site
must comply with all prescriptions concerning structural details, welding
procedure methods, preserving of base materials and weld material, execution
methods, personnel employed in welding activities, as well as the welded joints
and their testing as described in the items listed above.
Particular care must
be taken in protecting groove edges against rusting and in providing
appropriate protective shelter during welding operations, with the use of
suitable equipment. This is especially important when different methods are
used other than shielded electrode welding; in this case the Constructor will
provide for adequate procedure that must describe all the protection means
against atmospheric agents in the area where welding is performed.
2
Maximum care must be taken the study and assembly of
the joints and edge preparation to ensure correct execution of all joint
welding. Precise instructions must be furnished by the metal structure
constructor for these aspects.
3 The welding procedure envisaged for assembly welding will generally be
manual welding with basic homologated shielded electrodes, and similar to the
base material for mechanical and chemical characteristics.
Other procedure is
permitted on condition that the instructions in item 1 are observed after
obtaining Railway authorisation.
4
Welders working in on site welding positions must be
qualified. Tests proving welders’ capacity may be requested on site especially
in the case of particularly important joints or joints to be welded in
positions with difficult access, with the execution of pre-production test
plates.
5 Joints performed on site will be controlled using similar methods to
those applied in the workshop; the same criteria for extended controls apply in
the case of negative joint welding results. In any case, butt joints on main
structures executed on site must be subjected to magnetoscope and ultrasound
control checks.
6 On
resistance class S355 steel joints, or those of higher classes, and with Sc
combined thickness greater than 100 mm, non-destructive control checks must be
performed no earlier than 48 hours after welding operation completion.
All welded joints
will be visually controlled, and also controlled using the equipment
appropriate to the joint type, the kind of fault or defect that may be present,
and the work location, according to the present instructions.
As a rule,
instrumental control checks include magnetoscopic, X-ray and ultrasound tests on the finished joint, and a
control check with penetrating liquids only on surfaces with grooving on the
reverse side of full penetration joints. Final instrumental control checks are
performed after satisfactory visual checks as a rule.
Generally ultrasound
controls on full penetration butt joints will be performed on thicknesses over
30 mm. For thicknesses up to 30 mm , normally testing will be performed using
X-rays, and where necessary integrated with ultrasound controls for elements
subject to particular stress.
1 Non-destructive
control test personnel qualifications
The personnel charged
with non-destructive testing of welded joints must possess at least level 2
certification according to EN 473
standards. Alternatively, at least level 2 ASNT or CICPND certification could
be accepted.
1 Visual
control check
Visual
control checks will be performed according to
EN 970 standards.
2 Magnetoscopic
control checks
Magnetoscopic control checks will be performed .
3 Penetrating
liquid control checks
Penetrating liquid control checks will be performed.
4 Ultrasound tests
4.1 Sensitivity setting
Sensitivity
grading for tests will be performed by tracing a reference curve at “constant
amplification” using the methods.
4.2 Sample block
The
reference block for sensitivity setting must have the same thickness, (with a
tolerance of ± 10%), as the greatest thickness of all the elements that compose
the joint to be tested.
4.3 Execution methods
Normally ultrasound testing on welded joints
will be performed by the WS or the authorised organisation. The execution
methods are generally those of best class. In any case, for assembly and
construction stages it must be kept in mind that it will be necessary to
perform control tests when the majority of the joint surfaces are not
accessible (for example in full penetration cross joints and T joints, the main
joint must be controlled before the welding of the second core, to permit
access to the platband of the part opposite the core that was welded first).
The examination
methods must be specified clearly in the control report.
4.4 Reflector registration.
All the reflectors
that produce a response with an amplitude greater than or equal to 20% of the
reference curve for control sensitivity, must be carefully analysed to define
the geometrical characteristics of any faults or defects, to form a supposition
on its nature and to evaluate it in terms of acceptability.
All the
non-geometrical indications with an amplitude over 20% of the reference curve
must be registered in the test report
Registration of the
test report must be performed so that the zones where response variations were
registered are easily identifiable, for example, using a coordinate system with
origins based on a punched reference mark.
Normally all welding must be visually
controlled 100%.
The Constructor is
bound to describe in an appropriate document the complete range of
non-destructive instrumental control checks he intends applying on production
jointing, with explicit reference to an established railway bridge;
alternatively, the indications describing the range of control checks may also
be included on the construction technical drawings.
The
control check range program must be approved by the Railway after approval by
the organisation charged with control procedure.
Normally the program to be followed is that
described in the points below.
1 Corner
seal or partial penetration joints.
Magnetoscopic control checks
will be performed by the Constructor on 100% of the joints on all the more
important bridge structures, and recorded in the test report.
The WS or another
authorised organisation will perform control checks in a testing plant, limited
to 30% of the length of every seal of each joint, whether corner seals or
partial penetration; this procedure may be increased according to the type of
welding method used and the results of the tests performed.
2 Full
penetration joints.
The magnetoscopic
control checks will be performed by the Constructor on 100% of the full
penetration butt or T joints, and recorded in the test report. The Constructor
will also perform ultrasound tests on at least 50% of the length of each joint.
Different procedure may be approved by the WS as established
in item 3.4.8.2. for particularly important joints because of
structural statics or because of particular stress, in other words, wherever
control checks must be extended to 100% because of the nature and entity of the
stress.
The WS or another
authorised organisation will perform magnetoscopic control checks in a testing
plant, on 30% of the length of all seals, and ultrasound control checks on 100%
of the established percentage. Intensification of control checks after negative
results
Whenever
any faults are revealed through instrument control checks on samples, all
controls are intensified. Normally a welding section on each side of the faulty
area is examined for a distance of at least 100 mm, but keeping in mind the
type of fault and the importance of the structural element. Further control
checks will be performed using at least the same method that revealed the
defect.
All
repairs executed with or without welding must be recontrolled using the same
method that revealed the defect; the zones where the unacceptable defects were
found using ultrasound control, must also obviously be recontrolled using the
same method that revealed the defect; furthermore at least two other sections
must be controlled for each repaired section, these sections will be chosen by
the testing personnel.
In
cases where repairs are numerous, or where unacceptable systematic faults are
discovered, the structural elements or the joints in question will be
eliminated.
When
the presence of systematic defects cannot be attributed to unsatisfactory
execution methods or lack of capacity on behalf of the welder or the machine
operator, the constructor must repeat his qualification procedure.
In any case, the constructor must
provide for the replacement of the eliminated joints; the new joints must be
recontrolled using the same method that revealed the defect, on twice the
quantity as that prescribed initially.
All
welding seams must be regular, smoothly attached to the base material and
without excess metal. The defect acceptability criteria are described in detail
below.
1
Visual control checks
The
quality of the welding seams controlled visually must comply with the
acceptability criteria established in
EN 25817 standards, group B, for first class joints and group C for
second class joints.
2 Magnetoscopic Control checks
The quality of the welding
seams controlled using a magnetoscope must comply with the acceptability
criteria established in EN 25817
standards, group B, for first class joints and group C for second class joints.
3 Ultrasound control checks
The acceptability criteria for application to
defects detected by ultrasound control checks must comply with the following
prescriptions:
a)
– reflectors which according to the echo position and characteristics are
interpreted as cracks, lamella tearing, lack of complete penetration, lack of
correct fusion with edges, will not be accepted, regardless of the response
amplitude.; elongated discontinuity localised at the vertex of welded seams and
at a distance equal to the thickness of the platband, compared to the external
face of the platband, will be considered as lacking in penetration if these
cannot be classified by US control as scoria;
b) – elongated reflectors with echo amplitude greater
than or equal to 150% of the reference curve will not be accepted;
c) – elongated reflectors with response echo amplitude
between 80% and 150% of the reference curve will not be accepted if;
• their
length results greater than ½ S, where S is the minimum thickness among those
connected to the joint in question with a maximum of 8 mm, for S lower than or
equal to 25 mm;
their length results greater than
1/3 S, with a maximum of 15 mm, for S
greater than 25 mm;
• the total length of the reflectors in
the welded section of 400 mm, with the greatest proportion of defects results as being longer than 20 mm;
• Two adjacent reflectors with respective lengths
L1 and L2, at a distance “d” will be considered as a single length defect of
length (L1 + L2 + d), if d ≤ (L1 +
L2) and if the response amplitude of at least one of the two defects is greater
than or equal to 80% of the reference curve.
Surface and profile
defects may be eliminated, even without having to perform new welding
operations if the depth of the defects does not exceed 10% of the thickness in
question ( or the least of the thicknesses in question, when the defect is in
the molten joint zone), but in any case the depth must not exceed 2 mm.
The defect can be
eliminated through grinding; this must be controlled visually with great care,
and in the case of doubt, with a magnetoscope; the hollowed surface must be
well smoothed with the adjacent material.
The Constructor must draw up one or more repair
procedures for welded joints for approval in the same manner as the welding
execution procedure.
This procedure must
include at least the means and methods
to be adopted for gouges or hollows, the pre-heating temperature, and
all aspects concerning the envisaged welding procedure.
Hollows must be ground
with a grindstone or carbon electrode and compressed air blast (arc-air)
followed by leveling grinding. The surface of the hollow must comply with all
previously described requisites.
As for spot welding, the pre-heating and interpass
temperature will be 25°C higher than the established temperature for joint
welding, according to approved welding procedure.
The welding procedure to be adopted is normally
basic homologated manual shielded electrode welding, with chemical and
mechanical characteristics similar to those of the base material.
Continuous arc welding could be used to repair
welded joints with hollows longer than 250 mm.
For weld material preserving and welding
techniques, refer to the indications provided for production welding.
Tightly drawn seams are not permitted (specific HI
< 0.8 KJ/mm) to fill hollows or scratches in order to prevent excessive
local hardness.
Repairs must provide smooth surfaces well attached to
the adjacent material; where necessary added seams or repairs should be
smoothes using a grindstone or button mill cutter.
Appropriate
extensions in the same material as the beams, must be included on 30% of the
beams welded in the workshop (production test end plates) . The WS also reserve
the right to request the application of production test plates on joints executed on site.
The production test plates
will be used to measure the hardness in
molten areas, in thermally altered areas, and in the basic metal, as well as
evaluation of correct welding penetration.
The methods and
extent of macrographic control checks on production test end plates will be
defined by the Constructor through appropriate procedure that will be presented
and approved by the WS after approval by the appointed control organisation. Normally these control checks are
performed on samples according to a percentage to be defined in the procedure
described above. For the joints executed in the workshop this
percentage cannot be less than 5% of the welded joints; for joints executed on
site, the number of tests will be established each time according to the type
of joint, the thickness, and the welding method applied.
Normally the procedure should provide for the
execution of macrographic controls on suitable production test plates, including
in the following cases:
• welding procedure application by the
Constructor for areas where there is no
consolidated applicative experience;
· During
initial stages of automatic or robot method application.
Hardness tests will be performed in at least
three points in the same area (basic material, molten area, thermally altered area) and it must be proved
that the Vickers hardness test ( HV10)
does not exceed the limits established in the certification procedure in any
point.
Records containing all
welding work must be kept by the Constructor according to EN 729 standards, describing all details and
circumstances concerning the work performed .
These records must contain a
list of all the welding activities performed, all repairs, the names of each
welder, the welding methods used (parameters, materials, pre-heaters, etc) any
intermediate control checks, and any other aspects that may be considered
useful for the contract work.
These records must be shown to the control personnel on work completion:
copies of the records will be delivered to the Railways representatives for
start-up tests and to be kept in the contract work files.
Generally
all holes are drilled with a suitable reduced diameter (at least 2 mm) and are
then bored or reamed to the final diameter after the girder to be built is
assembled completely with all the appropriate assembly pins and bolts.
Bolted joints on strongly static
structural elements such as main beams, diaphragms, torsion bracing etc. must
be foreseen using the following methods:
Slot bolts
with precision coupling, with hole-bolt play no greater than 0.3 mm including
the relative tolerance when no setting under joint load is admitted according
to Europe Directive CEE 189/1983.
Friction
bolts with a friction coefficient equal to 0.3, can be adopted in cases where
rails are to be laid with ballast, and on flyovers.
Bolts must be mounted on site with the head on the upper side and with a
washer under the screw head (beveled in the direction of the screw head), as
well as a washer under the nut (beveled in nut direction).
Various types of bolts ( slot or friction type) can be used on the same structure.
Project design plans
and workshop drawings must provide clear instructions for hole drilling and the
relative maximum tolerance levels.
Misaligned holes that do not permit the passage of the
appropriate bolt are forbidden.
For the perpendicularity between the bolt axis and the bolted surface, a
deviation of ≤ 3° is permitted.
All bolts
must be adequately tightened and especially:
Bolts subject to axial load: tightening to 100%.
Bolts subject to slotting
only: an 80% reduction of the official value is permitted, on condition that
instructions are provided on adequate precautions against self- loosening of
the bolts where necessary. However, in all cases vertical axis bolts must
always be mounted with the heads on upper side.
As far as
equipment and methods for bolt tightening are concerned, refer to the same
instructions as those foreseen for friction joints.
Misaligned
holes that do not permit the passage of the appropriate bolt are forbidden. Oval drilling of holes is not permitted and
in the case of difficulty, the hole diameter must be increased and a larger
bolt inserted.
For the perpendicularity between the bolt axis
and the bolted surface, a deviation of
≤ 3° is permitted.
All bolts
must be carefully tightened to 100% of the official value. Careful control
checks must be performed on bolt tightening and appropriate certification must
be issued. The prescriptions in relation to this aspect are provided below:
Bolts can
be tightened using pneumatic spanners on condition that said spanners are
equipped with torque limit devices;
Tightening
control checks must be performed using a dynamometric spanner, or some other
suitable instrument that guarantees precision to ± 10%. This control must be
made on 20% of the bolts, selected so that it covers all joints in question.
Even if only one single bolt does not comply with tightening standards, control
checks must be made on 100% of the joint bolts.
Any bolts
that result tightened with a torque greater that 5% over the prescribed value
will be eliminated and replaced.
Bolt tightening operations
will be performed as follows:
a) The
joint must be placed in the final position using an appropriate number of
“plugs” able to stiffen the joint suitably and to ensure that holes are in
correct alignment;
b) Bolts
will be tightened with a torque equal to 60% of the prescribed value beginning
with the bolts inside the joint and proceeding towards the external bolts;
c) Tightening
to 100% torque in the same order as that described above.
Bolt tightening control checks will be performed as follows:
a) Marking of the nut, screws
and plate to identify the relative positions;
b) Loosening
of the nut with a 60° rotation taking great care not to rotate the screw. The
screw head must be held securely from the opposite side;
c)
Nut tightening with the prescribed torque and a
control check to ensure that it returns to its original position.
For tolerance and processing quality providing for H11
tolerance for screw diameter. (See previous item)
All bolts complete with washers must be immersed in a suitable
protective substance compatible with the proposed painting cycle.
For
pieces to be curved, curving operations must be performed hot (bright red) and
pieces must be left to cool slowly.
It is
forbidden to continue curving operations on pieces that are no longer bright
red.
Lastly,
when plates and wide plates (or the strips cut from sheet metal) are united to
form composite structures (such as T beams) these must be appropriately
finished with suitable machining action to respect the dimensioning in the
drawings and the prescribed tolerance levels.
The WS will also control the
dimensions of the single pieces to ensure that they correspond with project
dimensions, taking prescribed tolerance levels into consideration.
The tolerance levels described in the table in Fig. 2
are applicable to all welding and welded element dimensions .
Tolerance levels for assembled elements.
The following tolerance levels are
applicable to assembled elements:
stiffener straightness:
+/-
4 mm for h less than or equal to 2000 mm;
+/- 8 mm for h greater than 2000 mm
-bolted
joints:
+/- 1 mm of level difference between the parts to be
joined and planarity difference between the adjacent parts in contact; - reverse
deflection
-0, +15% of the theoretical reverse deflection
As well as pieces that present production defects, the
WS reserve the right to also refuse pieces on which even one single dimension
is less than that prescribed , although keeping in mind the admitted tolerance
level, and the Constructor will be responsible for all charges and obligations
as a result of faulty pieces.
It is clearly understood that all material used to
replace refused pieces must be previously tested using the same methods as the
accepted pieces, already described in this article, and the Constructor will be
solely responsible for any delay in respecting contract terms.
Structures
must be painted with two coats of rust-proof, non-polluting paint with a zinc
phosphate base (C.T. 101) and two coats of synthetic paint (C.T. 111), or
cooked linseed oil based paint, as decided by the WS. Each coat must have a
thickness no less than 4 micron when dry.
The rust-proof paint must be applied in the workshop once the metal
surfaces have been sanded to almost white level. The RAL colour for the various
coats will be decided by the Principal.
All paint must be mixed frequently to ensure that the pigment does not
settle in the bottom of the container.
Once they have been sanded, the surfaces in contact with the friction
joints must be protected with a suitable adhesive film or with a special paint
approved by the WS, until they are assembled on site. These preparations must
be specified in the work plans.
Any chipping or damage to
paint during assembly work will be touched up on the work site.
The Constructor must issue the Railways with a detailed project plan and
program, outlining the procedure he intends following for metal structure
assembly and installation. Another safety construction must be provided under
the structure for operator’s safety and for convenient control check operations
on the assembled structure.
As well as
all the control checks to be performed according to instructions in the
previous section, during the assembly stage all assembly work must be
controlled to prevent any defects that can occur frequently, as listed
below:
·
inversion or change of element
position;
·
shape correction using flame
equipment, resulting in element forcing;
·
failure to provide the
packing foreseen in the project design;
·
dirty or soiled joint cover
surfaces;
·
bolts that are not tightened
correctly;
• bolting sequences that are not followed in
correct order (for example: from interior to exterior for joint covers);
·
elements assembled out of
square ( horizontal and vertical);
·
non-corresponding holes;
·
unstable temporary girder
supports;
·
element assembly using spot
welding;
·
on site welding that is not
foreseen or that is performed incorrectly;
• welding performed on rusty,
painted, or galvanised surfaces, or surfaces that are not adequately prepared;
• insertion of inadequately
dimensioned packing ( for example- only between external parts or visible
surfaces) ;
·
failure to repaint surfaces
under staking areas;
• connector welding without
adequate material pre-heating and without surface preparation;
·
insertion of bolts with size
and length not in compliance with project specifications;
• replacement of deformed, un-usable or missing elements, with others
with uncertain mechanical and chemical characteristics;
·
repairs on elements using
operations that will compromise element integrity;
·
non-authorised on-site
welding;
·
incomplete welding on
connectors ( collars);
·
paint that does not adhere
to the support;
·
painting performed on site
outside the approved cycle;
·
welding procedure not
suitable for the assemble stage in question;
·
Failure to clean the water
draining holes;
• spot welding for reinforced
concrete rods on connectors or platbands on mixed steel – concrete structures;
·
Final supports not perfectly plane;
· material
handling using devices that risk material deformation and/or cutting (e.g:
cutting by scarfing clippers);
• failure to clean (sanding) the
upper platband surfaces on mixed steel –concrete structures;
·
defects as a result of
incorrect material transport procedure on site;
• defects and distortion in certain
structural elements as a result of incorrect structure installation, especially
in sundry items;